Westwood Indoor Tennis Centre opened for business on 25 March 2008. The building includes four indoor tennis courts with changing facilities, disabled changing, first aid room, coaching and administration office and a spectator viewing gallery.
- First BREEAM Excellent building on campus.
- Top of the range blue acrylic cushion floor.
- The roof is curved over the main hall and supporting side accommodation.
Essential Information
Start & Finish dates |
Completed summer 2008 |
Funded by |
Capital Plan, Major Maintenance, LTA, Sport England, University Benefaction Fund |
Budget |
£2.5M |
Requested by |
Warwick Sport |
Managed by |
Estates Office |
Architects |
Berman Guedes Stretton Architects |
Quantity Surveyors |
Jacobs |
Mechanical Engineers |
Gez Hunter (Estates Office) |
Electrical Engineers |
Gary Price (Estates Office) |
Structural Engineers |
ARUP |
Main Contractor |
Interclass plc. |
Landscaping |
Estates Grounds Maintenance |
Statistics
Basic Building Cost |
£680/m2 |
Services Costs |
£189/m2 |
External Works |
N/A £/m2 |
Gross Floor Area |
2945m2 |
Total Area of Site |
0.42 hectares |
Function Areas and Their Size |
N/A m2 |
Electricity Consumption |
65kWh/m2 |
Gas and Heat Consumption |
24kWh/m2 |
Low Carbon Energy Generation |
No |
Water use |
240m3/year |
Steps taken to reduce environmental impact |
N/A |