Temporary traffic and pedestrian restrictions on Library Road and Lord Bhattacharyya Way from Monday 7th October 2024 - Friday 28th February 2025

The University of Warwick is currently delivering The Connect Programme, an unprecedented £700m investment in campus facilities. As part of the first phase, STEM Connect, construction enabling works are currently underway.

As part of these works, some temporary changes have been made to the way our community navigates our Campus. These are set out in more detail below.

From Monday 7th October, there will be traffic management and road/pathway closures on Library Road and Lord Bhattacharyya Way for essential road trenching. Accessible bays, service bays and pedestrian pathways will be temporarily closed during these phases, with alternative provisions in place.

Phase 3: 12/11/2024 - 12/12/2024

3-way traffic lights will be in operation on Lord Bhattacharyya Way between the Energy Innovation Centre, Library Road junction and WMG Concourse with a single lane closure.

  • The pathway closest to Engineering & Energy Innovation Centre will be closed.

Phase 4: 12/12/2024 - 28/02/2025

2-way traffic lights will be in operation on Lord Bhattacharyya Way between the Energy Innovation Centre & Library Road junction with a single lane closure.

  • The pathway closest to Engineering & Energy Innovation Centre will be closed.
  • The crossing near the Lord Bhattacharyya Way junction will be temporarily set back further down Academic Loop Road with a signalised crossing.
  • The pathway between Physics/Materials and Analytical Sciences and Gibbet Hill Road will be closed.

Alternative Routes:

  • All affected areas will have clearly signposted detours and alternative routes in place.

An image of Library road and Lord Bhattacharyya Way showing the areas affected for the period of the 4 phase works.