Introduction

‘Hot works’ requiring permits are all temporary operations involving open flames or producing heat and/or sparks. This includes, but is not limited to, brazing, welding, cutting, grinding, thawing, and the use of heat guns.

As part of these works you as the fire watch person are required to carry out a continuous fire watch after the completion of all hot works for a minimum of 1 hour, during this time the site of the hot works must not be left unattended.

The declaration below confirms that you have carried out the required fire watch for the task being carried out as part of the stated Hot Works permit (please refer to the written instruction within the hot works permit). You are also confirming you have removed all sensor caps and any alarms that have been deactivated are fully reinstated and working correctly before leaving site.

Privacy notice
This form is anonymous. No data which personally identifies you is collected on the form, and the data you provide is used solely to help us improve the delivery of our courses.

The University of Warwick is the Data Controller of any information you have entered on this form and is committed to protecting the rights of individuals in line with Data Protection Legislation. The University's Data Protection webpages provide further information on your rights and how the University processes personal data. If you wish to submit a data subjects rights request, make a complaint or report a suspected personal data breach, please contact the University’s Data Protection Officer by email at infocompliance@warwick.ac.uk.

Spam prevention

Failure to load reCAPTCHA

reCAPTCHA is a utility used to verify you're not a robot filling out this form. Unfortunately this has failed to load correctly.

Please try reloading the page. If the problem persists, or if you are in a country which blocks Google products, please contact us by using the ‘page contact’ link at the foot of this page.