Campus Timeline:Benefactors Refurbishment (2016)
This was the first major refurbishment of the Benefactors building since it was constructed in 1966 – one of the first buildings on campus.
Benefactors is now among the highest quality accommodation available on campus, offering self-contained apartments, shared accommodation and a ground floor social area for its residents. We've also worked a great deal on the outside of the building too, giving it a modern look and much improved surrounding landscape so that it better fits with our recently developed Benefactors Place plaza area.
As ever, sustainability was a key consideration in this project. We've connecting the building to the campus heating network, powered by our efficient combined heating and power plant to cut down on energy consumption.
Essential Information
Start & Finish dates | April 2015 – April 2016 |
Funded by | CCSG |
Budget | £4m |
Requested by | Warwick Accommodation |
Managed by | Estates Office |
Architects | Associated Architects |
Quantity Surveyors | Sweett Group |
Mechanical Engineers | Couch Perry Wilkes |
Electrical Engineers | Couch Perry Wilkes |
Structural Engineers | Associated Architects |
Main Contractor | Management Cubed |
Landscaping | Management Cubed |